We will design a replacement bridge for 205th Avenue at Beaverton Creek.
We will begin with a traffic analysis to determine if the road needs to be widened to three lanes (one motor vehicle travel lane in each direction and a center turn lane) or five lanes (two motor vehicle lanes in each direction with a center turn lane).
Additional improvements include:
- Bike lanes
- Sidewalks
- Retaining walls
- Guardrails
- Street lights
- Improved storm drainage
- Storm water treatment facilities
Design start: September 2022
Design finish (expected): Spring 2026
Construction start (expected): Summer 2026
Construction finish (expected): Fall 2027
Sign up to receive project updates by email
Update
9/6/2024: Design is about 60% complete. We are planning an open house for fall.
Funding
Cost Estimate: $1.3 million (design); $24.1 million (to complete)
Funding source (design only): Major Streets Transportation Improvement Program (MSTIP 3e)