Housing Authority of Washington County
Community Partners for Affordable Housing
Take a look at how the Grand Opening celebration was like here. For more on the project, check out the press release that went out before it opened to the public.
Total Development Cost: $10M
Funding Sources: $9.3M Metro Affordable Housing Bond, Housing Production Opportunity Fund, Oregon Housing and Community Services Multifamily Energy Program
54 units consisting of:
- 54 Studios, 370 sq. ft
All units for those at 30% AMI
Reconstruction Start: December 2021
Reconstruction Completion: April 2023
This special project was made possible by two voter-approved regional housing measures: the 2018 Affordable Housing Bond and 2020 Supportive Housing Services Levy.
For community members who had questions about Heartwood Commons, the County conducted a virtual community meeting that can be seen here.