Skip to main content

Cornell Road (102nd to 113th Avenue)

Cornell Road is being improved between 102nd and 113th avenues. Construction began in 2022.

We widened Cornell Road to three lanes, one lane in each direction with a center turn lane, between 102nd and 113th avenues. These improvements address bike and pedestrian safety and traffic flow.

We also installed a traffic signal at the Cornell Road and 107th Avenue intersection. Additional improvements include continuous sidewalk and bicycle facilities, street lighting and storm drainage upgrades.

Construction start: Feb. 15, 2022
Construction finish: August 2023

Sign up to receive project updates by email 

Update

10/16/2023: Construction is complete.

Funding

Cost Estimate: $12.9 million

Funding Source:

County Major Streets Transportation Improvement Program (MSTIP 3d)

Prior events and comment opportunities

Online open house: Feb. 11-27, 2022

Open house: June 25, 2019

New exhibit: Nov. 27, 2018

Open house: June 28, 2018

Contact(s)

Back to top