149th Avenue (Watershed Lane to Farmington Road)

We will complete sidewalks along 149th Avenue to provide safer pedestrian access to local schools, parks and commercial areas.

We will build sidewalks along the east side of 149th Avenue between Watershed Lane and Farmington Road.

Improvements may include:

  • Curbs
  • Curb ramps
  • Signage
  • Stormwater sewer

Design start: Spring 2025
Design finish (expected): Fall 2026
Construction start (expected):Summer 2026
Construction finish (expected): Fall 2026

Sign up to receive project updates by email

Update

9/25/2025: We are at about 30% design. We will be communicating with any property owners who have structures extending into the right-of-way that will need to be removed.

Funding

Cost Estimate: $400,000 (2024 estimate)

Funding source : Road Fund