19th Avenue (Council Creek-20th Avenue)

We will improve safety on 19th Avenue in Cornelius.

19th Avenue is one of five main entry points to the City of Cornelius. The street developed over time with inconsistent improvements, and lacks sidewalks and bicycle lanes along most of this section. 19th Avenue will provide local access and link downtown Cornelius to the future Council Creek Regional Trail.

The improvements include:

  • Mini roundabout at 19th Avenue and Holladay Street to improve traffic flow
  • Bulb-outs and narrowed pavement to reduce traffic speed
  • Sidewalks with ADA-complaint curb ramps
  • Bike lanes
  • Street lighting
  • Tie into the future Council Creek Regional Trail
  • Improved stormwater facilities

Design start: October 2025
Design finish (expected): September 2027
Right-of-way start (expected): September 2026
Right-of-way finish (expected): September 2027
Construction start (expected): January 2028
Construction finish (expected): April 2029

Update

6/23/2026: Design is progressing and we expect to reach the 30% milestone later this summer. An open house is being planned for early fall.