Skip to main content

Bonita Road and Sequoia Parkway Intersection

We are adding a traffic signal to the Bonita Road and Sequoia Parkway intersection.

The Bonita Road and Sequoia Boulevard intersection, near I-5, is a busy intersection in Tigard. We will install a traffic signal to improve safety and traffic flow.

Other improvements include:

  • Crosswalks
  • ADA-compliant curb ramps
  • Some storm drain updates

Design start: June 2024
Construction start: June 15 2026
Construction finish (expected): Sept. 30, 2026

Update

6/11/2026: Construction is starting. Expect lane closures 9 a.m.-3:30 p.m. weekdays. Traffic may be held up to 10 minutes at a time.

Visit wc-roads.com for current traffic impacts.

Commissioner District 3

Funding

Cost estimate: $1.6 million

Funding source: Major Streets Transportation Improvement Program (MSTIP 3e)

Major Streets Transportation Improvement Program (MSTIP)

Prior Comment Opportunities

Contact(s)