We will infill sidewalk in locations along both sides of this segment of road where there is no sidewalk. We will also build curb ramps, add signage and improve drainage in some locations.
This project will improve pedestrian connectivity in the Aloha area and will improve access to nearby schools, parks and businesses.
Construction start (expected): Summer 2027
Construction finish (expected): Winter 2027
Update
9/25/2025: We have completed initial survey and are nearing 30% design.
Funding
Cost: $2,700,000 (2025 estimate)
Funding source: Road Fund