We will replace the culvert with a stronger one and repair the roadway in preparation for the Old Pumpkin Ridge Road Road Reconstruction. The culvert will also meet Oregon Department of Fish and Wildlife standards for fish passage. We expect Old Pumpkin Ridge Road will close during construction.
Construction start (expected): August 2025
Construction finish (expected): September 2025
Update
6/12/2025: We are bidding for a construction contractor.
Funding
Cost: $545,000 (2024 estimate)
Funding sources:
Contact(s)