A traffic signal is needed to improve safety at the River Road and Witch Hazel Road intersection.

We are installing a traffic signal at the River Road and Witch Hazel Road intersection.

The signal provides important traffic flow and safety improvements near a Clean Water Services wastewater treatment facility.

The project includes ADA-compliant curb ramps and pedestrian crossing signals.

Design start: November 2025
Construction start (expected): July 2026
Construction finish (expected): October 2026

Update

6/11/2026: Construction is expected to start in early July. Expect intermittent daytime lane closures.

Funding

Cost estimate: $1.24 million

Funding source: Utility Reimbursement