Comment on the Walker Road Phase 3 Project through Dec. 13

Comment on the Walker Road Phase 3 Project at an online open house through Dec. 13.
Media release

For Immediate Release: Friday, November 27, 2020

Sponsored by: Department of Land Use and Transportation

Comment on the Walker Road Phase 3 Project at an online open house through Dec. 13.

Walker Road will be widened to five lanes (two travel lanes in each direction with a center turn lane) with bike lanes and sidewalks between 173rd and 185th avenues.

The project also includes: 

  • Replacement of a culvert at Willow Creek
  • Removal of a dip in road at the culvert
  • Installation of a traffic signal at the Walker Road and 178th Avenue/Cambray Street intersection 
  • Installation of soundwalls
  • Improvements to drainage and street lighting

The $10.5 million project is funded through the County’s Major Streets Transportation Improvement Program (MSTIP 3e).

To participate in the open house, visit the Walker Road Phase 3 Open House or contact Capital Project Services at 503-846-7800 or [email protected].

Washington County is committed to planning, building and maintaining a great transportation system, ensuring the safety of all roadway users, and operating the County roadway system in cost-effective and environmentally responsible manner.

Media Contact:

Heather Sturgill, Senior Communications Specialist/PIO
503-846-7822
[email protected]
Back to top