Paving Begins August 17

Media release announcing 2015 overlay paving starting August 17, 2015
Media release

For Immediate Release: Tuesday, August 11, 2015

Paving schedule update
UPDATED: 09/04/2015
Sponsored by: Department of Land Use and Transportation, Capital Project Services Division

Update: 9/4/15

The following roads are scheduled for paving:

  • 170th Avenue - Rigert to Blanton - Sept. 4 through Sept. 14
  • Fern Hill Road - OR 47 to Blooming Fern Hill - Sept. 15 to Sept. 16
  • Kemmer Road - 170th to Mayberry - Sept. 17 to Sept. 18

 


Original release: 8/11/15

Paving work will be performed on several major County roads beginning Monday, August 17. Roads will remain open, but may be limited to one-way traffic controlled by flaggers. Expect up to 15-minute delays. Use alternate routes if possible.

The following roads are scheduled for nighttime paving from 8 p.m.-6 a.m. Monday-Friday, August 17-21:

  • 170th Avenue – Blanton Street to Tualatin-Valley Highway
  • 185th Avenue – Shaw Street to Tualatin-Valley Highway
  • 185th Avenue – Tualatin-Valley Highway to Alexander Street

Roads scheduled for daytime paving this fiscal year (through June 30, 2016) include:

  • 119th Avenue – Cornell Road to McDaniel Road
  • 170th Avenue – Rigert Road to Blanton Street
  • 175th Avenue – Scholls Ferry Road to Kemmer Road
  • 185th Avenue – Bridge over Beaverton Creek at Pheasant Lane
  • Bald Peak Road – Laurelwood Road to Orchaedia Drive
  • Fern Hill Road – Blooming Fern Hill Road to Highway 47
  • Glencoe Road – West Union Road to North Avenue
  • Grabhorn Road – Tile Flat Road to Stonecreek Drive
  • Kaiser Road – Thompson Road to Purvis Drive
  • Kemmer Road – 170th Avenue to Mayberry Place
  • Kinnaman Road – Farmington Road to 185th Avenue
  • McCormick Hill Road – Laurel Road to Vanderschuere Road
  • Miller Hill Road – Gassner Road to Farmington Road
  • Rigert Road – 185th Avenue to 160th Avenue
  • Steppingstone Drive – 185th Avenue to Baseline Road
  • Tile Flat Road – Scholls Ferry Road to Grabhorn Road

Daytime paving will generally occur from 8 a.m.-6 p.m. For the latest paving schedule, visit www.wc-roads.com. Advisory signs will be posted before the work begins. The schedule is subject to change due to weather or other unforeseeable circumstances.

For more information contact Kim Haughn, public information officer, at [email protected] or 503-846-7800.

Washington County is committed to planning, building and maintaining a great transportation system, ensuring the safety of all roadway users, and operating the county roadway system in a cost-effective and environmentally responsible manner. 

Media Contact:

Melissa De Lyser, Communications Coordinator
503-846-4963
[email protected]