We will add a crosswalk, signs, road striping and curb ramps.
A Rectangular Rapid-Flashing Beacon (RRFB) will be installed to alert drivers when someone is in the crosswalk. RRFBs are crossing signals with blinking lights that turn on when a pedestrian presses a button.
This project is part of a larger effort to connect sidewalks and walkways in the Bethany area.
To ensure cost-efficient construction, this project is being designed and constructed alongside:
- Waterhouse Trail Crossings
- Laidlaw Road and Waterhouse Trail
- Kaiser Road and 147th Avenue
- Greenwood Drive
Construction start (expected): Winter 2024
Construction finish (expected): Summer 2025
Update
4/18/2024: Design is 30 percent complete. We will now be designing and constructing this project alongside crosswalks on the Waterhouse Trail to ensure cost-efficient construction. Construction is now expected to begin fall 2024.
Funding
Cost: $200,000 (2021 estimate)
Funding source:
Contact(s)
Name | Title | Phone | |
---|---|---|---|
Capital Project Services |