As part of a multi-year project, we will raise the height of the guardrail and improve end treatments on several of our arterial roads.
In 2025, guardrail will be replaced in these locations:
- April 14-16, May 21-23, 26: Spring Hill Road from Highway 47 to Gibson Road
- April 17-18, 21-22: Patton Valley Road from Lee Road to Mount Richmond Road
- April 22-23, April 28-May 2, May 28: Stringtown Road from Gales Creek Road to B Street
- April 23-25, 28: Ritchey Road from Stringtown Road to Pacific Avenue
- May 2, 27-29: Susbauer Road from Hornecker Road to 19th Avenue
- May 5-9: Cornelius Schefflin Road from Long Road to Wren Road
- May 12-14: Glencoe Road from Harewood Street to Highway 26
- May 15-16, 19-20: Jackson School Road from Evergreen Road to Mason Hill Road
Update
4/7/2025: Guardrail replacement is scheduled to begin April 14. Expect intermittent lane closures.
Funding
Cost: $500,000 (2022 estimate)
Funding source: