We are designing improvements for 170th Avenue, including:
- Replacing the bridge over Beaverton Creek
- Adding a center turn lane
- Installing bike lanes
- Installing sidewalks
We are also considering a traffic signal at Augusta Lane and pedestrian crossing signal at either Vendla Park Lane or Johnson Street.
The project team is working with Tualatin Hills Park & Recreation District to minimize the impacts to the park and improve the entrance on 170th Avenue.
Alternatives analysis start: July 2022
Alternatives analysis finish (expected): Fall 2022
Design start (expected): Summer 2022
Design finish (expected): Spring 2025
Construction: Dependent on funding
Sign up to receive project updates by email
Update
3/6/2024: The county is reevaluating potential transportation project construction dates due to funding constraints and rapidly increasing costs. This process is expected to take several months.
Funding
Cost: $3.12 millions (2022 estimate)
Funding source: Major Streets Transportation Improvement Program (MSTIP 3e)