We will build sidewalks along the west side of the road that will connect to Farmington Road. This project is part of a larger effort to connect sidewalks and walkways in the Aloha area.
Construction start (expected): March 2023
Construction finish (expected): October 2023
Update
1/11/2023: Design work for this project is 60 percent complete.
Funding
Cost: $359,000 (2022 estimate)
Funding sources:
Prior events and comment opportunities
Online open house: Oct. 21- Nov. 6, 2022
Contact(s)
Name | Title | Phone | |
---|---|---|---|
Capital Project Services |