We will build sidewalks along the west side of the road that will connect to Farmington Road. This project is part of a larger effort to connect sidewalks and walkways in the Aloha area.
Construction start (expected): Summer 2024
Construction finish (expected): Fall 2024
Update
9/13/2023: Project design is nearing completion. We are preparing for right-of-way acquisition.
Funding
Cost: $359,000 (2022 estimate)
Funding sources:
Prior events and comment opportunities