195th Avenue (FY 2022-24 Pedestrian & Biking Improvement)

The sidewalks on 195th Avenue from Keena Court to Farmington Road don’t all connect.

We will build sidewalks along the west side of the road that will connect to Farmington Road. This project is part of a larger effort to connect sidewalks and walkways in the Aloha area. We will build this in conjunction with the 188th Avenue sidewalk project.

Construction start (expected): July 14, 2025
Construction finish (expected): Aug. 22, 2025

Update

8/13/2025: This project is substantially complete. Our contractor may be on site for some final tasks.

Funding

Cost: $359,000 (2022 estimate)

Funding sources:

Urban Road Maintenance District (URMD)

Prior events and comment opportunities

Online open house: Oct. 21- Nov. 6, 2022