We will replace the 205th Avenue bridge at Beaverton Creek, between Baseline Road and Quatama Street.
Additional improvements include:
- Buffered bike lanes
- Sidewalks with ADA-compliant curb ramps
- Retaining walls
- Guardrails
- Street lights
- Improved storm drainage
- Storm water treatment facilities
The bridge replacement will require a full road closure, planned for 2027.
Design start: September 2022
Design finish: January 2026
Construction start (expected): June 2026
Construction finish (expected): December 2028
Sign up to receive project updates by email
Update
5/11/2026: Meet the project team at an open house from 5-7 p.m. Thursday, May 28 at R.A. Brown Middle School, 1505 SW Cornelius Pass Road.
Construction will begin next month and continue through 2028.
205th Avenue will be closed for bridge replacement, beginning July 2027 and is expected to continue through October 2028.
Funding
Cost Estimate: $24.2 million
Funding sources:
- Major Streets Transportation Improvement Program (MSTIP 3e, MSTIP 3f)
Comment opportunities
Updated Pedestrian Detour
Open House: May 15, 2025
Open House: Nov. 22-Dec. 8, 2024
Newsletters