205th Avenue (Baseline Road to Quatama Street)

205th Avenue is narrow between Baseline Road and Quatama Street. A bridge over Beaverton Creek needs to be replaced.

We will replace the 205th Avenue bridge at Beaverton Creek, between Baseline Road and Quatama Street.

Additional improvements include:

  • Buffered bike lanes
  • Sidewalks with ADA-compliant curb ramps
  • Retaining walls
  • Guardrails
  • Street lights
  • Improved storm drainage
  • Storm water treatment facilities

The bridge replacement will require a full road closure, planned for 2027.

Design start: September 2022
Design finish: January 2026
Construction start (expected): June 2026
Construction finish (expected): December 2028

Sign up to receive project updates by email

Update

5/11/2026: Meet the project team at an open house from 5-7 p.m. Thursday, May 28 at R.A. Brown Middle School, 1505 SW Cornelius Pass Road.

Construction will begin next month and continue through 2028.

205th Avenue will be closed for bridge replacement, beginning July 2027 and is expected to continue through October 2028.

CPO 7
Commissioner District 1

Major Streets Transportation Improvement Program (MSTIP)

Funding

Cost Estimate: $24.2 million

Funding sources:

Pedestrian detour during bridge replacement

Comment opportunities

Updated Pedestrian Detour

Open House: May 15, 2025

Open House: Nov. 22-Dec. 8, 2024

Newsletters

May 2025