We will design a replacement bridge for 205th Avenue at Beaverton Creek, between Baseline Road and Quatama Street.
Additional improvements include:
- Buffered bike lanes
- Sidewalks with ADA-compliant curb ramps
- Retaining walls
- Guardrails
- Street lights
- Improved storm drainage
- Storm water treatment facilities
The bridge replacement will require a full road closure.
Design start: September 2022
Design finish (expected): January 2026
Construction start (expected): Summer 2026
Construction finish (expected): Fall 2028
Sign up to receive project updates by email
Update
12/19/2025: Right-of-way acquisition is in progress. We expect to advertise for construction contractor in February.
Funding
Cost Estimate: $24.2 million
Funding sources:
- Major Streets Transportation Improvement Program (MSTIP 3e, MSTIP 3f)
- Transportation Development Tax
Comment opportunities
Open House: May 15, 2025
Open House: Nov. 22-Dec. 8, 2024