Alexander Street is in unincorporated Aloha, north of TV Highway. This street provides a slower travel option that is preferable for pedestrians and cyclists.
Improvements will include:
- Add street markings for shared pedestrian and vehicle lanes
- Install alternate parallel parking and landscaping on both sides of the street
- Sidewalks on both sides of the street
- Upgrade stormwater drainage
- Install a bike/pedestrian crossing signal at the 185th Avenue and Alexander Street intersection
- In-fill sidewalk between 192nd and 202nd avenues creating a complete sidewalk connection west to 209th Avenue (added summer 2025, details below)
Design start: Summer 2022
Design finish (expected): Fall 2026
Right-of-way start (expected): Fall 2025
Right-of-way finish (expected): Winter 2026-27
Construction start (expected):Spring 2027
Construction finish (expected): Fall 2028
Sign up to receive project updates by email
Update
10/9/2025: We have updated this project to include additional sidewalk segments (infill) between 192nd and 202nd avenues. See the letter and maps, below.
Funding
Cost Estimate: $25 million
Funding source: Major Streets Transportation Improvement Program (MSTIP)
Alexander Street sidewalk infill
During the summer of 2025, the County Engineer directed staff to include in-fill sidewalk between 192nd and 202nd avenues to create a sidewalk connection west to 209th Avenue. Information about the project was mailed to impacted property owners in October.