This project involves construction of a new sidewalk or pedestrian pathway along Augusta Lane, between Pheasant Lane and Chatelain Drive, to provide a safe walkway for pedestrians separated from traffic.
This project is being constructed with the Augusta Lane Pedestrian Bridge Project.
Construction start (expected): Jan. 2021
Construction finish (expected): 9/30/2021
Update 10/26/2021
Construction is complete
Funding
Cost: $201,000 (2020 estimate)
Funding source:
Prior events and comment opportunities
Construction kickoff Jan 22-31, 2021:
Open house April 6-26, 2020: