We are widening Century Boulevard, north and south of TV Highway, to five lanes with bike lanes, sidewalks, improved drainage, street lights, landscaping, signs and striping. Upgrades to the rail crossing, traffic signal and bus stops on TV Highway will also be included with this project.
Construction start: July 19, 2021
Construction finish: December 2022
Sign up to receive project updates and open house announcements.
Update
12/10/2022: Construction is significantly complete.
Funding
Cost: $14.6 million (2021 estimate)
Funding Sources:
- MSTIP Bonding Cost-Sharing Program
- Utility reimbursement
- City of Hillsboro
- Development fee
- CPO 9 (inactive)
- Commissioner District 4
Prior events and comment opportunities
Construction kickoff open house 6/18-7/5/2021
Open house 6/13/2019:
- Century Boulevard strip mall
- Tualatin Valley Highway strip mall
- Century Boulevard road closure
- Schedule
- Typical sections
Detour maps