We are widening intersection to keep up with increasing traffic from bicycles, pedestrians and vehicles.
This includes:
- Adding dedicated turn lanes from southbound 25th Avenue onto Cornell Road
- Adding bicycle lanes
- Updating street lights and traffic signals
Construction start (expected): July 2023
Construction finish (expected): July 2024
Update
12/5/2022: Right-of-way is still in progress. We hope to bid for a construction contractor in May.
Funding
Cost: $5.9 million (estimate)
Funding sources:
- Major Streets Transportation Improvement Program (MSTIP 3d)
- City of Hillsboro
Design
January 2017: Concept design map

CPO 9 (inactive)
Commissioner District 4
Contact(s)