The Thatcher Road intersection with Gales Creek Road (OR-8) will be realigned for improved sight distance and prepare the intersection for a future traffic signal (not part of this project.)
We will also install:
- A crosswalk across Gales Creek Road with a Rectangular Rapid Flashing Beacon (RRFB)
- A sidewalk on the north side of Thatcher Road between pathway at Snapdragon Lane and Gales Creek Road
- A sidewalk on the south side of Gales Creek Road between Talisman Lane and the crosswalk
- A paved pad for GroveLink bus stop
Construction start (excepted): Spring 2024
Construction finish (expected): Fall 2024
Sign up to receive project updates by email
Update
5/23/2023: Our right-of-way process is continuing. Construction has been delayed to 2024.
Funding
Cost: $1.1 million (2021 estimate)
Funding sources:
- County Trust and Agency Funds
- City of Forest Grove
Prior events and comment opportunities
Contact(s)
Name | Title | Phone | |
---|---|---|---|
Capital Project Services |