Miller Hill Road Pedestrian Improvement

We will installing in-fill sidewalks on Miller Hill Road.

We are installing sidewalks and curb ramps between existing sidewalks on the east side of Miller Hill Road, between Georgene Court and Sonia Lane.

There are sidewalks near Hazeldale Elementary School and near a recent housing development. We will install two sections of sidewalk to create a continuous pedestrian route between Farmington Road and Gassner Road.

Construction start (expected): Spring 2024
Construction finish (expected): Fall 2024

Update:

3/24/2023: We are about 30% of the way through design. We are planning an online open house June 16-July 2.

Funding

Cost: $600,000 (2020 estimate)

Funding sources:

Contact(s)