We are installing sidewalks and curb ramps between existing sidewalks on the east side of Miller Hill Road, between Georgene Court and Sonia Lane.
There are existing sidewalks near Hazeldale Elementary School and near a recent housing development. We will install two sections of sidewalk to create a continuous pedestrian route between Farmington Road and Gassner Road.
Construction start: June 4, 2025
Construction finish (expected): July 31, 2025
Sign up to receive project updates by email
Update:
6/9/2025: Construction is underway. The contractor is expected to communicate driveway impacts directly with homeowners.
Funding
Cost Estimate: $963,808
Funding sources: Gain Share
Newsletters
Prior events and comment opportunities
Contact(s)
Name | Title | Phone | |
---|---|---|---|
Capital Project Services
|