The culvert on Pleasant Valley Road is in need of replacement. We will be replacing the existing culvert with a 24-inch plastic pipe.
We are not planning to close the road during construction. Flaggers will be present 7:30 a.m.-5 p.m. weekdays. Anticipate two-way, single-lane travel.
Construction start (expected): 8/23/2021Construction finish (expected): 9/24/2021
Update
This project is complete.
Funding
Cost: $200,000 (2021 estimate)
Funding sources:
Contact(s)
Name | Title | Phone | |
---|---|---|---|
Road Maintenance |