Skip to main content

Pongratz Road Culvert Replacement

This project is complete.

The culvert on Pongratz Road, between Tolke Road and Ardabeth Lane, is too small and often clogs. We are replacing the culvert with a larger metal pipe to improve water flow and allow fish to pass upstream.

We are replacing the culvert at the same time as the bridge over Whitcher Creek, east of Tolke Road. More information about the bridge replacement is available on the project page

The project is starting in summer 2021 (tentative) and ending in October. Pongratz Road will close during construction. 

Construction start (expected): Aug. 2021
Construction finish (expected): 9/30/2021

Update

This project is complete.

Funding

Cost: $450,000 (2020 estimate)

Funding sources:

Prior events and comment opportunities 

Contact(s)

Back to top