Skip to main content

Thompson Road (Saltzman Road to Marcotte Road)

We will add bike lanes, sidewalks and a center turn lane to Thompson Road between Saltzman Road and Marcotte Road.

We will widen Thompson Road between Saltzman and Marcotte roads with a center turn lane, bike lanes and sidewalks.

Other improvements include updated:

  • Street lighting
  • Traffic signs
  • Striping
  • Storm drainage
  • Water quality facilities

Design start: October 2022
Design finish (expected): December 2023
ROW acquisition (expected): December 2023-Fall 2024
Construction start (expected): Fall 2024
Construction finish (expected): Fall 2025

Sign up to receive project updates by email 

Update

3/21/2023: Survey is work is nearing completion. Our design consultant is working on design options.

Funding

Cost: $6.6 million (2021 estimate)

Funding sources:

Contact(s)