Thompson Road (Saltzman Road to Marcotte Road)

We will add bike lanes, sidewalks and a center turn lane to Thompson Road between Saltzman Road and Marcotte Road.

We will widen Thompson Road between Saltzman and Marcotte roads with a center turn lane, bike lanes and sidewalks.

Other improvements include updated:

  • Street lighting
  • Traffic signs
  • Striping
  • Storm drainage
  • Water quality facilities

Design start: October 2022
Design finish (expected): February 2025
Start right-of-way acquisition (expected): February 2025
Construction start (expected): January 2026
Construction finish (expected): May 2027

Sign up to receive project updates by email

Update

7/10/2024: The bike and pedestrian alternatives were presented to the Board of County Commissioners at their July 9 Work Session. We are reviewing feedback and continuing design.

The timeline has been updated.

Funding

Cost Estimate: $6.3 million

Funding sources: