We will widen Thompson Road between Saltzman and Marcotte roads with a center turn lane, bike lanes and sidewalks.
Other improvements include updated:
- Street lighting
- Traffic signs
- Striping
- Storm drainage
- Water quality facilities
Design start: October 2022
Design finish (expected): June 2026
Start right-of-way acquisition (expected): January 2026
Construction start (expected): December 2026
Construction finish (expected): December 2027
Sign up to receive project updates by email
Update
12/19/2025: Right-of-way acquisition will start this winter. All impacted property owners will be contacted directly by a right-of-way agent for Washington County.
Email us with questions or for help accessing the exhibits.
Funding
Cost Estimate: $8.6 million
Funding sources:
- MSTIP Bonding Cost-sharing Program
- Bonny Slope West System Development Charge
Sight distance exhibits
Prior events and comment opportunities
Open House: April 14, 2025
- Project design map (PDF 19.5 MB)
- Cross sections (PDF 3.9 MB)
- Schedule (PDF 720 KB)
Online open house: June 9-29, 2023
CPO Presentation: March 2023
Online open house: May 1-17, 2020
Contact(s)
| Name | Title | Phone | |
|---|---|---|---|
|
Capital Project Services
|