We will widen Thompson Road between Saltzman and Marcotte roads with a center turn lane, bike lanes and sidewalks.
Other improvements include updated:
- Street lighting
- Traffic signs
- Striping
- Storm drainage
- Water quality facilities
Design start: October 2022
Design finish (expected): February 2025
Start right-of-way acquisition (expected): February 2025
Construction start (expected): January 2026
Construction finish (expected): May 2027
Sign up to receive project updates by email
Update
7/10/2024: The bike and pedestrian alternatives were presented to the Board of County Commissioners at their July 9 Work Session. We are reviewing feedback and continuing design.
The timeline has been updated.
Funding
Cost Estimate: $6.3 million
Funding sources:
- MSTIP Bonding Cost-sharing Program
- Bonny Slope West System Development Charge
Prior events and comment opportunities
Contact(s)
Name | Title | Phone | |
---|---|---|---|
Capital Project Services |