Skip to main content

Thompson Road (Saltzman Road to Marcotte Road)

We will add bike lanes, sidewalks and a center turn lane to Thompson Road between Saltzman Road and Marcotte Road.

We will widen Thompson Road between Saltzman and Marcotte roads with a center turn lane, bike lanes and sidewalks.

Other improvements include updated:

  • Street lighting
  • Traffic signs
  • Striping
  • Storm drainage
  • Water quality facilities

Design start: October 2022
Design finish (expected): June 2024
ROW acquisition (expected): May 2024-February 2025
Construction start (expected): March 2025
Construction finish (expected): August 2026

Sign up to receive project updates by email 

Update

11/22/2023: The estimated project timeline has been updated.

We will present design options to the Board of County Commissioners at a future Board meeting.

Funding

Cost: $6.6 million (2021 estimate)

Funding sources:

Prior events and comment opportunities

Online open house: June 9-29, 2023

Contact(s)

Back to top