Skip to main content

West Union Road shoulder widening project

This project is complete.

The shoulders on both sides of West Union Road are very narrow. We will widen the shoulders, between NW Helvetia and NW Cornelius Pass roads, by about 4 feet on each side of the road. In addition, we will also make pavement repairs and add an asphalt overlay.

West Union Road is a highly used route, with a 66.17% increase in traffic volume since 2010. Adding wider shoulders will improve safety for vehicles, farm equipment, bicycles and pedestrians. The new asphalt overlay will extend the life of the road.

We do not plan to close West Union during construction, but there will be lane closures. Expect delays.

Construction start (expected): 4/5/2021
Construction finish (expected): 7/6/2021

Update 9/2/2021

This project is complete.

Funding

Cost: $1.8 million (2020 estimate)

Funding source:

​​​​​​Road Fund

Contact(s)

Back to top