We will widen Cornell Road to three lanes, one lane in each direction with a center turn lane, between 102nd and 113th avenues. These improvements address bike and pedestrian safety and traffic flow.
We will also install a traffic signal at the Cornell Road and 107th Avenue intersection. Additional improvements include continuous sidewalk and bicycle facilities, street lighting and storm drainage upgrades.
Construction start: Feb. 15, 2022
Construction finish: July 2023
Sign up to receive project updates by email
Update
7/31/2023: This project is significantly complete. Punch-list work will correct any minor issues.
Funding
Cost: $13.1 million (2021 estimate)
Funding Source:
County Major Streets Transportation Improvement Program (MSTIP 3e)
Prior events and comment opportunities
Online open house: Feb. 11-27, 2022
Open house: June 25, 2019
- Design map
- Schedule
- Project information
- Existing traffic volumes
- Future traffic volumes
- Typical sections
- Right-of-Way process
New exhibit: Nov. 27, 2018
Open house: June 28, 2018
Contact(s)
Name | Title | Phone | |
---|---|---|---|
Capital Project Services |