Kaiser Road (Springville Road to Brugger Road)

We will widen Kaiser Road, between Springville Road and Brugger Road.

We will improve Kaiser Road, between Springville and Brugger roads, with a center turn lane, on-street bike lanes and standard sidewalks. We will also add sidewalk along County-owned property on Brugger Road, near Kaiser Road.

We will also install:

  • Street lights
  • Storm drainage
  • Water quality facilities
  • ADA-compliant curb ramps

A traffic study will be done during the design phase. We will evaluate the need for an enhanced crosswalk at the intersection of Kaiser and Brugger roads.

Design start: April 2023
Design finish: Fall 2025
Construction start (expected): May 2026
Construction finish (expected): December 2027

Sign up to receive project updates by email

Update

3/9/2026: Construction is expected to begin in May. The detour route has been updated. Drivers will detour to Germantown Road, 185th Avenue and Springville Road.

Download detour map:

Funding

Cost Estimate: $7.8 million

Funding source: North Bethany County Service District for Roads (NBCSDR)

Planned detour during Kaiser Road closure

Prior events and comment opportunities

Updated detour map March 9, 2026:

Open house Jan. 25, 2024: