We will improve Walker Road between 173rd and 185th avenues with five lanes, two travel lanes in each direction and continuous center turn lane, with bike lanes and sidewalks.
Other improvements include:
- Replacing the culvert at Willow Creek
- Raise grade of road at Willow Creek crossing by 8-10 feet to improve sight distance and rideability
- Building a traffic signal at 178th Avenue/Cambray Street
- Upgrading storm drainage
- Improving street lighting
- Installing some sound walls
- Installing landscaping
This is the third phase of capacity improvements to Walker Road.
Construction start (expected): January 2026
Construction finish (expected): Spring 2028
Sign up to receive project updates by email
Update
5/8/2025: Utility relocation is expected to begin in late summer. Construction will start in 2026.
Also see: Walker Road Projects
Funding
Cost Estimate: $25.6 million
Funding sources:
- Major Streets Transportation Improvement Program (MSTIP)
- City of Beaverton
Prior events and comment opportunities
Online open house: Nov. 30-Dec. 13, 2020
Updated design map: June 3, 2020
Open house: Aug. 8, 2018